Client: Dangote Refinery Company

Hydrogen Gas Unit

Year of Completion: Not stated

Dangote Refinery Company - Hydrogen Gas Unit

Client Challenge

The hydrogen gas unit reformer inlet pigtail found crack and needed to be repaired

Purpose

not available

Solution

Cutting, fabrication of the segmental piece; carry out proper welding procedure and approved as per WPS. Upon completion of welded joints, RT was conducted, and all joints were found passed.

Hydrogen Gas Unit
It is proposed to provide jump over connection between phenolic stripped water to return headers of CT-4 at SRU plant.

Health & Safety, Supplier Guiding Principles, and Contractor Management